Análisis del plan de gestión de tiempo y costo en la rehabilitación de alcantarillados con CIPP (Cured In Place Pipe) en Bogotá según el PMBOK 6ta edición
Fecha
Autor corporativo
Título de la revista
ISSN de la revista
Título del volumen
Editor
Universidad Distrital Francisco José de Caldas
Compartir
Director
Altmetric
Resumen
The project proposes the analysis of the schedule and cost management plan executed in a sewer rehabilitation project in the city of Bogotá through technology CIPP, the application project took place exactly in the Claret and Inglés neighborhoods of the town of Tunjuelito, with the development of this project it was possible to detect improvements in the planning and execution processes following the good practices of the PMBOK 6th edition, we are generating a cost management plan in which all the activities to execute are applied and a schedule management plan the activities of the intervention of a section that requires rehabilitation by the CIPP method.
Descripción
El proyecto plantea el análisis del plan de gestión del cronograma y los costos ejecutado en un proyecto de rehabilitación de alcantarillado en la ciudad de Bogotá a través de tecnología CIPP, el proyecto de aplicación tuvo lugar exactamente en los barrios Claret e Inglés de la localidad de Tunjuelito, con el desarrollo de este proyecto se lograron detectar mejoras en los procesos de planeación y ejecución siguiendo las buenas prácticas del PMBOK 6ta edición, al generar un plan de gestión de los costos en el que se apliquen todas las actividades para ejecutar y en un plan de gestión del cronograma se tengan detalladas las actividades de la intervención de un tramo que requiere rehabilitación por el método de CIPP.
Palabras clave
Curado de Tubería en Sitio, Alcantarrillado, Gestión del Cronograma, Gestión del costo, Sin zanja, Saneamiento, Rehabilitación