Aplicación de la gerencia de proyectos para planificación de recursos humanos con apoyo modelos BIM 5D. Caso de estudio: ampliación y remodelación de las instalaciones de una transportadora de valores.
Fecha
Autores
Autor corporativo
Título de la revista
ISSN de la revista
Título del volumen
Editor
Compartir
Director
Altmetric
Resumen
Currently, in Colombia, project management in construction is supported by traditional construction planning methods, which consist of programming theoretical execution times of activities based on the taking of manual work quantities that are prone to human error. Generally only in programs such as Microsoft Proyect that do not allow you to have a complete vision of the project, schedules are made that on several occasions lack logical sense at the constructive level. Therefore, we sought to implement the BIM 4D and 5D methods to integrate human resources within the project in a quantitative way to have a clear concept about what personnel are really needed within the work depending on the type of the construction process that is used in This case study is a reinforcement with a metal structure or concrete structure, where the costs and durations of the personnel in each activity will be found in real time in 3D model, which will allow to know what type of structure is more profitable in terms of Human resources